Jan de Nul have all but completed their work in front of the Ritz Carlton.
Photo, right, taken this afternoon by Jim Wehrle.
After frenetic progress since February 1st, work on the Cancún beach recovery has visibly slowed after three days of windy conditions and choppy seas.
However, the equipment will shortly be assembled at the Royal Sands, which is next in line for a beach makeover.
The project is now 60 per cent complete and still on course to reach Punta Cancún before the April 30th contract deadline.
- My unofficial beach recovery timeline


March 13th, 2006 at 6:14 am
Steve,
Just returned from GCPS… there was no work done while we were there from the 9th to the 12th. Winds prevented the ships from working. However they did work on assembling the piping to go forward. They should move quickly again when the winds die down.
ps. thanks for the site, we really appreciated it, and knowing our beach was completed really made our trip more relaxing
March 13th, 2006 at 10:11 am
Looks like you had a beach though.
Jim Wehrle took this photo in front of the Golden Crown Paradise on the 11th.