Beach update

Last updated: April 12th

Advisory: Jim Wehrle and I have guesstimated the following dates for beach "nourishment". We’ve done the best we can… based on Jim’s on-the-spot checks and my contact with individual hotels. Such is the speed of the recovery work, I’m updating this page constantly. Comments welcome, of course.

On April 11th, the crews returned to Playa Delfines for some remedial work.

shading indicates beach has been replenished

Note: Not all hotels are listed. Check the status of Cancún hotels.

Completed Started at El Mirador on 1 Feb
El Pueblito – March 21st, April 11th
Crown Paradise Club – March 21st
Completed Oasis Playa – March 21st
Solymar Beach Resort – March 5th, March 21st
Completed Solaris – March 5th, March 21st
Aristos
Hotetur Beach Paradise – March 16th
Sun Palace Resort 
Completed Westin Resort & Spa Cancún
Club Med Cancún
Punta Nizuc
Back to the Hilton for the start of phase 2
Hilton Cancún Golf & Spa Resort
Completed Royal Islander
Royal Caribbean – March 5th, March 11th
Royal Mayan – March 12th
OmniFeb 25th
Completed Oasis Cancún – March 5th
Grand Oasis
Fiesta Americana Condesa
Completed Gran Melia
Marriot CasaMagna – March 5th
JW Marriot
Completed Cancún Palace – March 11th
Le Meridien Resort & Spa – March 7th, March 11th
Golden Crown Paradise
Ritz Carlton Cancún
Completed The Royal Sands – March 15th, March 20th
Casa Turquesa
Barceló Tucancun Beach
Completed Villas Marlin
Fiesta Americana Grand Aqua
Completed Sheraton Towers/ Westin Lagunamar
Park Royal Piramides

Melia Turquesa

Beach Palace

Avalon Grand
Avalon Bacarra
Completed Flamingo
Grand Caribe Real

Hyatt Cancún Caribe

Le Blanc – April 4th, April 5th
Royal Sunset
Miramar (in process of demolition)
Forum by the Sea
Completed Krystal
Hyatt Regency Cancún
Punta Cancún

Disclaimer: I’m offering this information as a service. While I am continually updating this page, I reserve the right to make the occasional mistake. Thanks.